Two travel lanes will be maintained in both the northbound and southbound direction. Traffic will be controlled by temporary barriers.
As stated in a previous press release, starting on or after Saturday, May 20, the I-65 northbound exit ramp at State Road 47 will close. It’s expected to reopen at the end of December.
This contract was awarded to E & B Paving, LLC for over $83.7 million. It also includes bridge replacements near U.S. 52, a bridge removal near Lafayette Avenue, culvert work and drainage construction on I-65. The entire project is expected to be completed in December of 2023.