City Paving Starting September 6

The Frankfort Street Department will prepare for milling and paving next week with Reith Riley. Milling will begin on East Clinton Street and Clinton Drive on Wednesday, September 6.

“If the weather is on our side, we should have the paving completed in about seven days,” said Street Superintendent Jason Forsythe. I want to urge the community to be
patient and to avoid the construction zones as much as possible. “We will be working on trimming trees at the beginning of the week and putting up no parking signs Thursday.” If you have on-street parking, cars will be towed if they aren’t moved when milling and paving work begins.

Mayor Judy Sheets, Board of Public Works, and Street Superintendent Jason Forsythe approved the total of $648,805 in the spring of 2023 for these street projects:

• East Clinton Street from Clay Street to Fudge Avenue
• Clinton Drive from Fudge to Maish Road
• South First Street from White Street to West Walnut Street
• East Ohio Street from Crescent to Kelly Avenue
• McClurg Street from Myrtle Avenue to Rossville Avenue

This list does not reflect the order in which work will be completed. For updated information, visit the City of Frankfort or Frankfort Street Department Facebook page.