{"id":381997,"date":"2021-04-01T06:18:24","date_gmt":"2021-04-01T10:18:24","guid":{"rendered":"https:\/\/clintoncountydailynews.com\/?p=381997"},"modified":"2021-04-01T07:08:35","modified_gmt":"2021-04-01T11:08:35","slug":"381997-2","status":"publish","type":"post","link":"https:\/\/clintoncountydailynews.com\/381997-2\/","title":{"rendered":"28 Eastbound From Tracks to Jackson Closes April 1; Other 28 Closure Details Explained"},"content":{"rendered":"
Traffic on 28 in Frankfort is going to get messy starting Thursday, April 1. <\/span>All the disruption will be for a good cause and the entire west side of the Indiana 28 project (west of Jackson Street) will be done by November 1.<\/span><\/p>\n
Excellent progress and some relief will be obvious by mid summer, according to Steve Rothgerber with Fox Contractors Corp. Fox is a subcontractor for E&B Paving.<\/span><\/p>\n
Steve Rothgerber with Fox Contractors Corp. Background shows part of detailed drawing of the 17.2 million dollar 2 year project for 28 through Frankfort. Fox is subcontracting for E&B Paving.<\/figcaption><\/figure>\n
<\/p>\n
Starting April 1, Eastbound traffic on 28 from the railroad tracks near Schulz Market to Jackson Street will be closed for most of the summer. <\/span>Westbound traffic on 28 from Jackson Street to the railroad tracks will have one lane open.<\/span><\/p>\n
Eastbound 28 traffic coming into town will be diverted to McKinley Avenue by the Vintage Cafe (formerly The Island) to downtown starting April 1.<\/span><\/p>\n
The intersection of 28 and Jackson by The Farmers Bank and CVS will be closed for five days to put in a new storm sewer and water pipe. The intersection will then be opened up with temporary asphalt.<\/span><\/p>\n
\u201cThis is a dangerous job. Be patient with us. We\u2019re just doing our job. Drive slow. Keep us safe, we\u2019ll keep you safe. We\u2019ll try to keep you going the best we can,\u201d <\/span>said Steve Rothgerber with Fox Contractors Corp. “By summer you\u2019ll have a much better looking street and road in town\u201d <\/span><\/p>\n
200 West to Jackson will be done by November 1, 2021. Jackson through the city\u2019s east side will be completed in 2022. The complete project will cost 17.2 million dollars.<\/span><\/p>\n
Detail of intersection southeast of The Farmers Bank and Northwest of CVS. This intersection will be closed for 5 days.<\/figcaption><\/figure>\n","protected":false},"excerpt":{"rendered":"