The Indiana Department of Transportation will begin work on the northeast quadrant of I-465 next week.
Contractors will work to patch and repave segments of I-465 and I-69 from U.S. 31 all the way down to I-70.
This work is part of a Marion County Construction Plan that looks to erase winter damage done to area interstates. It’s part of a statewide winter damage plan.
Work is scheduled to begin next week after Memorial Day. Crews will be doing night and weekend work from the end of May through October.
Work will be completed in four different segments. Please use the map below for reference. At least one lane in each direction will always be open during this project.
Segments
Segment 1: I-465 E/W from White River Bridge to I-69
- End of May to Middle of August
- Crews will work on the eastbound inside lanes first
- Work will be completed on nights and weekends
- 8 p.m. to 6 a.m. the next morning
- One lane will always be open in each direction
Segment 2: I-465 E/W from U.S. 31 to White River Bridge
- Beginning of June to Middle of August
- Weekend lane closures
- 8 p.m. to 6 a.m. Monday morning
- One lane will always be open in each direction
Segment 3: I-69 N/S from I-465 to S.R. 37
- Middle of June to End of July
- Work will be completed on nights and weekends
- 8 p.m. to 6 a.m. the next morning
- One lane will always be open in each direction
Segment 4: I-465 E/W from I-69 to I-70
- Beginning of August through October
- Work will be completed on nights and weekends
- 8 p.m. to 6 a.m. the next morning
- One lane will always be open in each direction